Solar project pricing should be available soon

Written by Tony Herman, Hastings Tribune

Derek Zeisler, director of marketing and energy supply for Hastings Utilities, gave an update on the power project during the Hastings Utility Board meeting Thursday. Members of the Hastings Utility Board voted recommend approval during their February meeting of a $2.38 million bid from GenPro Energy Solutions for a 1.5 megawatt AC solar project with the purchase option. The project has a completion date of Sept. 2, 2019 . . . Zeisler said Thursday this first phase of the solar project will include more than 6,000 panels within three arrays, most likely off of Highland Road just west of the Hastings Municipal Airport. There is plenty of room there to
expand with future phases. Hastings Utilities is moving forward with three pricing options.
Read more here.